CGS upgradation at Chikhli City Gate Station

Detailed planning and coordinated execution for a critical Natural Gas metering upgrade.

Client
Maharashtra Natural Gas Limited
Location
Chikhli City Gate Station, Pune
Scope
12-inch USM and associated pipe spool replacement

PROJECT OVERVIEW

Upgrading infrastructure that keeps a city supplied

Greentech Engineers undertook the replacement of a 12-inch ultrasonic gas meter (USM) and associated pipe spool piece on the main incomer Natural Gas pipeline at MNGL’s Chikhli City Gate Station.

The project built on the team’s LPG skid fabrication and installation experience dating back to 2010, extending that capability into a large-diameter Natural Gas skid installation. The operating network, existing alignment constraints and short shutdown window shaped the execution plan.

Yellow gas pipework and metering equipment at the City Gate Station
Station pipework pictured in the project presentation

THE CHALLENGE

Preparing for a tightly controlled shutdown

An operating gas network

The existing skid supplied gas to Pune and surrounding industrial areas, including Chakan, Talegaon and Hinjewadi. The work had to be planned around a very limited shutdown window.

Existing alignment constraints

The project team identified an out-of-plumb skid and reported stress at the existing joints. Matching the entry and exit connections required close attention to the installation geometry.

Calibration and resource planning

USM calibration needed coordination with GAIL’s busy schedule. The presentation also records a 180 man-day constraint, making procurement, preparation and specialist staffing important.

OUR APPROACH

Precision before installation

  1. Secure materials early

    Place timely orders for pipes, fittings, valves and accessories so that procurement supports the planned installation work.

  2. Resolve the connection details

    Work carefully through the drawings to match the entry and exit joints hole-to-hole.

  3. Coordinate USM calibration

    Arrange a calibration slot with GAIL Hazira through active scheduling and coordination.

  4. Bring shutdown expertise to site

    Engage experienced technicians familiar with the demands of shutdown work.

  5. Maintain technical coordination

    Stay in close contact with the Honeywell team for guidance during the project.

Site team positioning a yellow pipe assembly with lifting equipment at the station
Coordinated site work during the CGS upgradation project

THE OUTCOME

Safe completion, recognised by MNGL

In its appreciation letter dated 27 May 2024, MNGL confirmed the safe and successful completion of the USM and pipe spool replacement. The client recognised the team’s diligence, commitment and leadership in overcoming the project’s challenges.

“The project outcomes have surpassed our expectations, and I cannot commend you enough for setting such a high standard.”
Manik Kadam · Vice President (Operations & Maintenance), MNGL

MNGL Appreciation Letter

27 May 2024 · Greentech Engineers

MNGL appreciation letter dated 27 May 2024, signed by Manik Kadam, recognising Greentech Engineers for safe and successful completion of the 12-inch USM and pipe spool replacement at Chikhli City Gate Station.
← Back to case studies